How much rig time/preparation is needed for your surface equipment - especially the skids?

Preparing a rig for EC-Drill® typically takes 6–7 months, with the Modified Riser Joint as the main lead item at about 6 months, plus minor rig modifications.

An ideal time frame would be 6 to 7 months to get a rig EC-Drill ready. The Modified Riser Joint is the largest lead item at around 6 months. Various rig modifications to flow lines, installing pad eyes, etc. are required.