How fast can EC-Drill® be mobilized?

EC-Drill® mobilization speed depends on equipment availability and rig integration time. The Modified Riser Joint is usually the longest lead item, typically requiring up to 6 months, though shorter lead times have been achieved.

With the popularity of EC-Drill®, the equipment is subject to availability. With available EC-Drill® equipment, the limiting factor will be rig integration time. The 3rd party modified riser joint is typically a longest lead item, with a usual lead time of 6 months, although 3 months lead time has been achieved on previous projects.